COMMERCIAL

IRONBANK COMMERCIAL DEVELOPMENT

CLIENT

Samson Corporation

VALUE

NZ 38 million

TIMESPAN

90 Weeks

ARCHITECT

RTA Studio

PROJECT MANAGEMENT

Styles Project Management

Construction                        

  • Concrete piled basement constructed using ‘top down’ construction techniques

  • Podium beams/slab supporting structural steel tower structures

  • Externally ship lap glazed lift shaft James Hardie Hardieflex Cavity cladding creating a water tight building envelope 

  • ‘Exaplate’ steel rain screen cladding all to predetermined sizesto allow pre weathering of steel prior to erection

  • Project achieved Green Star as built rating of 5

  • Specific designed glazed aluminium windows integrated with a James Hardie Hardieflex Cavity cladding creating a water tight building envelope

© 2019 Macrennie Commercial Construction   |   

+64 9 525 3330