DHL Healthcare Logistics

Industrial, All

DHL Healthcare Logistics

Construction of a 14,000m2 temperature controlled warehouse + 6,500m2 of breezeways.
Included in warehouse were cold chain, freezer, vault, high security area, DG 6&8, premix rooms.
Along with 500m2 Dangerous Goods (DG3), 800m2 Mezzanine, 200m2 plant room, and a 1200m2 A-Grade office and full-length canopy.
MCCL contracted by single sourced negotiated procurement.

Construction Details

  • 5 Star Design and Asbuilt rating


  • Preloaded platform with lime and cement stabilised subgrade to increase CBR


  • High stud Steltech portal frames


  • Post tensioned concrete warehouse slabs


  • Kingspan insulated panel roofing and wall cladding to warehouse


  • Low height precast panel to warehouse 


  • Structural steel mezzanine for MHE


  • Fusion rooftop package units to temperature-controlled warehouse


  • Kingspan PIR cold chain and ante rooms 


  • Kingspan freezer constructed to FM global specification with a frost heave heated insulated floor


  • Fully sprinklered building (warehouse, office, canopies)


  • Feature Altus aluminium windows

DHL Healthcare Logistics

Project Details

Client: Auckland International Airport Ltd

Timespan: 79 weeks

Project Manager: RDT Pacific Ltd

Architect: Williams Architects Ltd

Value: $60 million

Quantity Surveyor: RLB

Engineer: Day Consulting Ltd

DHL Healthcare Logistics