IKEA Distribution Centre

Construction Details

  • 5 Star Design and Asbuilt rating


  • Lime cement stabilised subgrade to lift CBR values


  • High stud Steltech portal frames


  • Low height precast panel to warehouse 


  • Sunken truck dock with Ulti rapid doors


  • Post tensioned concrete warehouse slab


  • Architecturally glazed office with MDS cladding to wrap around parapet


  • Fully sprinklered building (warehouse, office, canopies)


  • MHE charging station for 12no units


  • Heavy duty concrete yards with shared ROW

IKEA Distribution Centre

Project Details

Client: Auckland International Airport Ltd

Timespan: 47 weeks

Project Manager: RDT Pacific Ltd

Architect: Williams Architects Ltd

Value: $34 million

Quantity Surveyor: RLB

Engineer: Day Consulting Ltd