Construction of 11,000m2 of high stud freezer/chiller facilityand 4,000m2 of ambient warehouse with associated canopies complete and 600m2 of single level office and 2 0,000m2 of heavy duty yards. MCCL contracted under early contract engagement.
Construction Details
High stud clear span chiller and freezer facility
-28-degree freezer, -4-degree chiller
Major refrigeration installation including standalone plantroom
Insulated panel external envelope
15 no cross docks with rapid roller doors and dock revellers
Post-tension warehouse floor slab
Single storey office complex with architectural façade
Integrated electrical, fire, mechanical and refrigeration services
Extensive heavy duty yards, fencing and landscaping
Racking installation and integrated fitout
Project Details
Client: Auckland International Airport
Timespan: 50 weeks
Project Management: RTD Pacific
Architect: Eclipse Architecture
Value: NZ 28.3 million
Quantity Surveyors: ---